April 29, 2019

Vestas V90 3MW turbine

April 29, 2019

All seven turbines in Krzanowice are set up

January 22, 2019

Assembly of the rotor blades

January 16, 2019

The Godel of the visaVento Turbine

The heart of the turbine is ready to be built.

January 16, 2019

Construction of the Tower

The tower parts are set up slowly and very precisely.

January 16, 2019

The first tower piece of the 4 Turbine

The Turbine construction progresses.

September 17, 2018

Turbine transport

Three rotor blades with the steel tower on the way to Krzanowice.

September 7, 2018

The concrete works are completed

All four foundations are finished. After a curing time of three weeks, the turbine can be built.

August 13, 2018

New label of the gondola

The logo of the turbine manufacturer is removed and replaced by visaVento.

August 10, 2018

The first hub has already been delivered.

As the first of the turbine parts, the hub of a turbine was delivered on site. The remaining parts are expected as soon as the foundations are ready to concreted and loadable. Currently, it is waiting for cooler temperatures, as it is currently too hot for concrete work.