search
All seven turbines in position in Krzanowice Mounting the rotor blades The heart of the turbine is ready for assembly. The tower sections are slowly and very precisely put into position. Construction of the turbine is progressing. Three rotor blades and the steel tower on their way to Krzanowice. All four foundations are finished. After being left to set for three weeks, the turbine can be erected.